World’s First WHR System For DRI - HISMELT Process Commissioned

Views: 8     Author: Site Editor     Publish Time: 2016-12-01      Origin: Site

On September 30, 2015, JSDJ was awarded a contract (contract value - 11,300,000) by Shandong Molong Petroleum to deliver a waste heat recovery solution to their existing DRI (direct reduced iron) HISMELT process. This project was commissioned on November 17, 2016.

    With years of innovative experience in WHR, JSDJ engineers managed to successfully overcome two major challenges that came with this project: 1. High dust content within the gas itself (approximately 20 ~ 50 g / Nm3); 2. Gas pressure is at +100Kpa.  

This project adds another highlight to our ongoing journey in WHR field, because it is the first waste heat recovery system ever applied to HISMELT process in the world.

 

Key Parameters

Inlet gas temp: 800 Celsius

Outlet gas temp: 250 Celsius

Steam pressure: 4.5 & 0.6 MPA

Steam temp: 258.78 & 164.95 Celsius

Steam output: 63.2 & 26.5 T / H

WHR-for-Direct-Reduced-Iron-HISMELT-ProcessWHR-for-Direct-Reduced-Iron-HISMELT-Process1

QUICK LINKS

CONTACT US

Address:No. 9 Huarui South Rd, Yancheng, China, 224005
Tel:+86-515-88583229
Phone:+86 13375256375
Fax:+86-515-88583229
E-mail:don-davison@djzg.org
Manager: Don Davison   
Website: www.chinawasteheatboiler.com

Copyright  JSDJ Heavy Industry Co.,Ltd All rights reserved.