Successful commissioning of Inner Mongolia project - AQC Waste Heat Boiler
On August 20, 2016, JSDJ’s installation crew completed the erection work of a AQC waste heat boiler for a cement plant in Inner Mongolia. Shortly after, our on-site engineers along with client’s technical team witnessed the successful commissioning of this project.
Our WHRB was designed to recover the waste heat from the highly dust laden flue gas coming our of the clinker cooler. We took into consideration that the dust is particularly with high hardness, therefore, in order to prevent abrasion of the heat surface area, certain measures must be taken. As a result of this, our engineers optimized the flow velocity and strategically placed baffle plates & diversion devices to equalize the gas flow field. The main technical data are indicated below.
Key Parameters
Production Capacity: 3000 T / D
Inlet gas temp: 360 Celsius
Outlet gas temp: 135 Celsius
Steam pressure: 0.8 MPA
Steam temp: 260 Celsius
Steam output: 12 T / H
Address:No. 9 Huarui South Rd, Yancheng, China, 224005
Tel:+86-515-88583229
Phone:+86 13375256375
Fax:+86-515-88583229
E-mail:don-davison@djzg.org
Manager: Don Davison
Website: www.chinawasteheatboiler.com